Excavating Contractors Industry Terminology
Aggregate
Granular material (sand, gravel, crushed stone) used for base courses, drainage layers, and backfill. Selected for gradation, durability, and compaction characteristics.
Place 6 inches of aggregate base under the slab per the detail. Use washed aggregate around the underdrain to promote flow. We’re short 200 tons of 3/4-inch minus for the haul road.
As-built Survey
A post-construction survey documenting actual horizontal and vertical locations of installed work versus design, used for record drawings and verification.
Submit the as-built survey showing the final invert elevations. The owner will release retainage after accepting the as-builts. Update the BIM model with as-built pipe locations before paving.
Backfill
Material used to refill an excavation. Placed in layers (lifts) and compacted to specified density and moisture to achieve stability and limit settlement.
Backfill the trench in 8-inch lifts to 95% of Modified Proctor. Use select backfill around the structure and native elsewhere. Don’t backfill until the inspector signs off on the bedding.
Bench (Benching)
Horizontal steps cut into a slope or excavation to improve stability, manage drainage, or provide working platforms. Also an OSHA-approved protective system for certain soil types.
Bench the slope at 4-foot intervals to break up runoff. OSHA allows benching for Type A soils but not in Type C. We benched the cut to give the excavator a safe work platform.
Backfill
Material used to refill an excavation. Placed in layers (lifts) and compacted to specified density and moisture to achieve stability and limit settlement.
Backfill the trench in 8-inch lifts to 95% of Modified Proctor. Use select backfill around the structure and native elsewhere. Don’t backfill until the inspector signs off on the bedding.
Bench (Benching)
Horizontal steps cut into a slope or excavation to improve stability, manage drainage, or provide working platforms. Also an OSHA-approved protective system for certain soil types.
Bench the slope at 4-foot intervals to break up runoff. OSHA allows benching for Type A soils but not in Type C. We benched the cut to give the excavator a safe work platform.
Call Before You Dig (811)
The national one-call system that notifies utility operators to locate and mark their facilities before excavation. A legal requirement in the U.S. to reduce utility strikes.
File the 811 ticket at least 2 business days before mobilizing. The 811 marks expire next week; request a refresh. No digging until utilities are located and the 811 window has cleared.
Compaction
Mechanical densification of soil by reducing air voids using rollers, rammers, or vibratory plates. Verified by field density tests vs. Proctor values.
Achieve 95% of Maximum Dry Density per ASTM D1557. Increase moisture; the lift is too dry to compact. The roller can’t seat in the trench; use a jumping jack for compaction.
Cut and Fill
Earthmoving practice of excavating (cut) high areas and placing material in low areas (fill) to achieve design grades with minimal import/export.
Balance the cut and fill to minimize export. The model shows 10,000 cubic yards of cut and 8,000 of fill. Haul the excess cut to the designated stockpile for later use.
Dewatering
Temporary removal or control of groundwater or stormwater from excavations using sumps, wellpoints, or deep wells to maintain dry, stable working conditions.
Install a wellpoint system to lower the water table 6 feet. Pump the sump to keep the excavation dry during footing work. Discharge dewatering effluent through a sediment bag per SWPPP.
Differing Site Conditions (DSC)
Unforeseen physical site conditions that materially differ from those indicated or ordinarily encountered, potentially entitling the contractor to time/cost relief.
We encountered rock at 3 feet, contrary to the borings—submitting a DSC notice. The unmarked duct bank qualifies as a differing site condition. Document the DSC with photos and a sketch for the change order.
Erosion and Sediment Control (ESC)
Practices and measures that prevent soil erosion and keep sediment from leaving the site (e.g., silt fence, check dams, inlet protection, construction entrances).
Install silt fence and inlet protection before clearing. Maintain the stabilized construction entrance to minimize track-out. Update the ESC plan after the grading change.
Excavator (Hydraulic)
Tracked or wheeled machine with boom, stick, and bucket used for digging, lifting, and placing materials. Accepts attachments like breakers, thumbs, and compaction wheels.
Use a 30-ton excavator with a rock bucket for the mass cut. Swap to the quick coupler to run the compaction wheel. The excavator tail swing encroaches on the live lane—add barrier.
Field Density Test (FDT)
Onsite test (nuclear gauge or sand cone) to verify compacted soil density and moisture against Proctor values specified for the work.
The nuclear gauge shows 92%—we need another pass. Run a sand cone test where the gauge is not allowed. Submit today’s FDT results with the daily report.
Finish Grade
The final designed elevation and surface condition after fine grading, ready to receive topsoil, pavement, or structures.
Blue-tops mark the finish grade for the subgrade. Fine-grade the pad to plus or minus 0.10 feet. Hold the finish grade low to account for topsoil depth.
Geotextile
Permeable synthetic fabric used for separation, filtration, drainage, or reinforcement between soil layers. Available as woven or nonwoven types.
Place a nonwoven geotextile separator under the base course. Use woven geotextile for reinforcement over the soft subgrade. Overlap the geotextile by 18 inches at seams per spec.
GNSS/GPS Machine Control
Satellite-guided grade control systems on dozers, graders, and excavators that compare blade or bucket position to a digital terrain model for accurate grading.
Load the latest surface model into the dozer’s machine control. The rover shows we’re 0.15 feet high on subgrade. Machine control reduced staking and improved our production.
Hydraulic Hammer (Breaker)
A percussive attachment for excavators used to fracture rock or concrete when ripping or digging is not feasible.
Switch to the breaker to trench through the limestone. The breaker requires a higher-flow auxiliary circuit. Limit breaker time near the building and monitor vibration.
Hydrovac (Vacuum Excavation)
Non-destructive excavation that uses pressurized water or air with a vacuum to safely expose buried utilities and features.
Hydrovac the utility crossings to verify depth before trenching. Use air-vac instead of water to avoid saturated spoils. The owner requires hydrovac for all potholes within 5 feet of gas lines.
Import/Export (Soils)
Movement of soil to or from a site to achieve design grades and meet material quality requirements based on the earthwork balance.
Current balance shows 2,500 cubic yards of import. Export the wet, unsuitable material to the approved dump site. Account for shrink and swell when planning import/export.
Insurance Certificate (COI)
Document issued by an insurer verifying coverage (e.g., general liability, auto, workers’ comp) and limits, often including endorsements like additional insured and XCU.
Provide a COI listing the GC and owner as additional insureds. Verify XCU coverage is included for excavation activities. The COI must match contract limits before mobilization.
Job Hazard Analysis (JHA)
A structured assessment that breaks a task into steps, identifies hazards, and defines controls to reduce risk to acceptable levels.
Complete a JHA for trenching over 5 feet before work starts. Review the JHA at the tailgate and update controls daily. The JHA lists ladder access and atmospheric testing as controls.
Jurisdictional Wetlands
Wetlands regulated under the Clean Water Act; disturbance typically requires permits and compliance with mitigation and buffer requirements.
The Corps determined these wetlands are jurisdictional; a permit is required. Flag the wetland buffer before clearing limits are staked. Dewatering discharge cannot enter jurisdictional wetlands.
Kickout (Trench Wall Failure)
A sudden bulging or heaving at the base of a trench wall that can lead to a cave-in, often caused by toe instability or surcharge loading.
Signs of a kickout are visible at the toe—stop work and shore. The clay is softening; a kickout could undercut the trench box. Surcharge loads near the edge increase kickout risk.
Ladder Access (25-Foot Rule)
OSHA requirement for safe egress: in trenches 4 feet or more deep, provide a ladder or ramp so workers never have to travel more than 25 feet laterally to exit.
Place a ladder within 25 feet of workers in trenches 4 feet or deeper. Extend the ladder 3 feet above the trench edge per OSHA. Move the ladder as pipe laying advances to maintain access.
Mass Excavation
High-volume earthmoving using large excavators, scrapers, and off-road trucks to move big quantities efficiently.
The mass ex scope is 60,000 cubic yards with a scraper spread. Use a spotter and GPS to manage truck cycles in mass excavation. Stage stockpiles to reduce double handling during mass ex.
Moisture-Density Relationship (Proctor)
Laboratory compaction test (ASTM D698 Standard or D1557 Modified) establishing maximum dry density and optimum moisture content for compaction specifications.
The lab Proctor shows an optimum moisture of 12% at 125 pcf MDD. Recondition the fill to within tolerance of the Proctor curve. Use Modified Proctor (ASTM D1557) for the pavement subgrade.
NPDES Permit
National Pollutant Discharge Elimination System permit regulating stormwater discharges from construction sites; mandates BMPs, inspections, and documentation.
File the NOI and post the NPDES permit onsite. Weekly SWPPP inspections are required under the NPDES permit. Update the site map when BMPs change to maintain NPDES compliance.
Notice to Proceed (NTP)
Formal written authorization from the owner to begin work, which typically starts contract time and triggers scheduling and procurement activities.
The contract time starts 10 days after NTP. We cannot mobilize until the NTP is issued. Update the baseline schedule within 14 days of NTP.
OSHA 1926 Subpart P (Excavations)
Federal safety standard governing excavation and trenching, covering protective systems, soil classification, inspections, egress, and hazard controls.
Subpart P requires a competent person to inspect the trench daily. The protective system design must comply with Subpart P. Provide means of egress per Subpart P for trenches over 4 feet.
Over-excavation
Excavating below design grade to remove unsuitable or unstable material, then backfilling with specified structural material to restore support.
Over-excavate 2 feet and replace with compacted structural fill. The inspector directed an over-ex due to pumping subgrade. Track over-ex quantities for a potential change order.
Potholing
Exposing buried utilities at discrete points to verify horizontal and vertical locations, commonly using vacuum excavation or hand digging.
Pothole all utility crossings along the proposed sewer alignment. Record actual depths from each pothole for the as-builts. Use hydrovac for potholing within 5 feet of electric.
PPE (Personal Protective Equipment)
Equipment worn to reduce exposure to hazards, such as hard hats, eye and hearing protection, gloves, respirators, and high-visibility apparel.
Hard hats, high-visibility vests, and safety boots are minimum PPE. Add hearing protection when running the breaker. Confined space entry requires additional PPE and monitoring.
QA/QC (Quality Assurance/Quality Control)
Planned processes to prevent defects (QA) and verify conformance (QC), including procedures, inspections, testing, and documentation.
The QA/QC plan outlines submittals, inspections, and testing. QC verified compaction test results before paving. QA oversight ensures third-party testing is independent.
Quantity Takeoff (QTO)
Measuring and quantifying materials and work items from plans or models for estimating, procurement, and production planning.
Perform a QTO from the model for cut/fill volumes. QTO shows 1,200 linear feet of 8-inch sewer. Reconcile the QTO with addendum revisions before bid day.
RFI (Request for Information)
Formal question from contractor to designer/owner seeking clarification of drawings or specifications; responses may drive plan revisions or change orders.
Submit an RFI asking whether Type B or C bedding is required. The RFI response confirms the invert elevation change. Reference RFI-012 on the change order backup.
Right-of-Way (ROW)
Land corridor reserved for public infrastructure or utilities, dictating access rights, permitting, and limitations on construction activities.
Work within the city ROW requires a traffic control permit. Stage equipment outside the utility ROW to avoid fines. Verify ROW width before setting fence lines.
Schedule of Values (SOV)
A detailed breakdown of the contract price into pay items used for progress billing, change management, and cost control.
Submit the SOV by CSI division for billing. The owner approved the SOV—start pay app No. 1. Add a separate line in the SOV for dewatering.
Shoring
Temporary structural support for excavation walls using systems like trench shields, hydraulic shores, soldier piles and lagging, or sheet piles.
Install hydraulic shoring where sloping is not feasible. The shoring design calls for walers and struts. Inspect the shoring daily and after rain events.
Soil Classification (Type A/B/C)
OSHA soil stability categories used to determine allowable slopes and protective systems: Type A (most stable), Type B, and Type C (least stable).
The competent person classified the trench as Type C. Sloping at 1.5H:1V is required for Type C soils. Reclassify the soil after the rain; cohesion may have changed.
Subgrade
The prepared soil surface that supports a pavement section, slab, or base course; must meet elevation, density, and stability requirements.
Proof-roll the subgrade and undercut pumping areas. The subgrade must be within 0.10 feet of design. Protect the prepared subgrade from traffic and rain.
Trench Box (Trench Shield)
A prefabricated shield placed in a trench to protect workers from cave-ins; does not prevent movement but provides a safe work area.
Set the trench box to the required depth before entry. Ensure the box extends above the trench by 18 inches. Use spreaders sized to maintain clearance for the pipe.
Trench Sloping
Excavation protection method that cuts back the trench walls to a stable angle based on soil type and surcharge conditions.
Cut the slope at 1H:1V; soil is Type B per the competent person. Increase the bench width to control sloughing on the slope. Sloping isn’t possible here—switch to shoring.
Undercut
Removal of unsuitable or weak material below design subgrade to reach competent soils, followed by replacement with specified structural material.
Undercut 18 inches and backfill with crushed stone. The proof-roll failed; mark areas for undercut. Track undercut quantities for potential change order pricing.
Utility Strike
Contacting or damaging a buried utility during excavation, posing safety, environmental, schedule, and cost risks.
A near-miss utility strike occurred during fence post drilling. Report any utility strike immediately and secure the area. Potholing and 811 coordination reduce strike risk.
Value Engineering (VE)
A structured process to improve function or reduce cost/schedule by proposing proven alternatives that meet or exceed design intent.
VE proposal: use flowable fill instead of compacted stone backfill. The VE session identified a haul road re-route to cut fuel cost. Submit a VECP per the contract for shared savings.
Vibration Monitoring
Measuring ground vibration (e.g., peak particle velocity) from construction activities to protect adjacent structures and document compliance with limits.
Set geophones to log PPV during rock breaking. Maintain PPV below 0.5 in/s near the historic building. Include pre-construction surveys as part of vibration monitoring.
Waler
A horizontal structural member in shoring that distributes loads and connects vertical supports (e.g., sheet piles or soldier piles) to struts or tiebacks.
Install the steel waler to tie the sheet piles together. The shoring design shows double walers at mid-depth. Torque the waler connections to the engineer’s specs.
Weather Day
An excusable non-work day due to adverse weather, as defined by contract thresholds or historical averages, often granting schedule relief.
Today is an approved weather day; no liquidated damages apply. The contract allows 6 historical weather days in January. Document rain totals to justify a weather day request.
XCU Coverage
Insurance coverage for Explosion, Collapse, and Underground hazards that are often excluded or limited in general liability policies for excavation work.
Verify XCU coverage is not excluded from our GL policy. The owner requires XCU limits for all trenching work. Provide the XCU endorsement with the COI.
Related Topics
Further Reading
Was this page helpful? We'd love your feedback — please email us at feedback@dealstream.com.
