Industrial Rigging Industry Terminology

Alloy Chain (Grade 80/100/120)

Heat-treated alloy steel chain used for overhead lifting. Grades 80, 100, and 120 indicate increasing strength; components must be compatible and marked. Chain slings tolerate higher temperatures than synthetics and must be inspected for stretch, wear, and cracks; never field-weld repair.

Use Grade 100 chain slings for this high-temperature pick.; The chain tag shows a 2-leg, 1/2 in Grade 80 with a 60° angle WLL.; Remove that sling—one link is elongated beyond allowable.


ASME B30

A suite of consensus safety standards for cranes, hoists, slings, rigging hardware, and below-the-hook devices. Key parts include B30.9 (slings), B30.10 (hooks), B30.20 (BTH devices), and B30.26 (rigging hardware). Often referenced by OSHA and company policy.

Per ASME B30.9, this roundsling needs an ID tag or it’s out of service.; Reference B30.26 to check the shackle’s side-load limits.; The lifting beam must meet ASME B30.20 and be proof-tested.


Basket Hitch

A sling configuration where the sling wraps under the load with both ends attached to the hook/rigging. Often increases capacity versus a single vertical hitch, but stability and angle reduction factors apply; not self-tightening like a choker.

If we use a basket hitch at 60°, the leg tension goes up—check the table.; For that smooth cylinder, a basket hitch with anti-slip protection works well.; Don’t basket on a load that could roll; add a cradle or blocking.


Below-the-Hook (BTH) Device

An engineered device connecting the hoist hook to the load (e.g., lifting beams, spreader bars, clamps, magnets, vacuum lifters). Must be rated, tagged, inspected, and often proof-tested per standards like ASME B30.20.

The spreader is a BTH device rated for 20 tons at 20 ft spread.; Our coil lifter falls under ASME B30.20 requirements.; Have the magnet BTH inspected before the shift.


Blocking/Cribbing

Stacks of timbers or crib towers used to support and stabilize loads, jacks, or equipment. Built to keep load paths vertical and contact surfaces flat; spreads loads to the ground or structure.

Build a 3-2-3 crib before you lift off the skates.; Use hardwood blocking to spread the jack load on the slab.; Never place cribbing on an uneven or soft surface without a mat.


Bow Shackle

Also called an anchor shackle. The rounded body accommodates multi-leg connections better than a D-shackle. Rated by Working Load Limit (WLL) and pin type (screw, bolt). Side loading is limited and must follow manufacturer guidance.

Use a bow shackle at the master link to connect the 3-leg bridle.; No side-loading that bow shackle beyond the manufacturer’s limit.; Verify the shackle’s WLL matches our calculated leg load.


Center of Gravity (CG)

The point where the load’s weight acts. Rigging must position the hook above (or directly through) the CG so the load hangs level and stable. CG location drives pick point placement and sling length selection.

Shift the rear pick point forward—the CG is closer to the motor end.; Mark the estimated CG on the drawing for the pre-lift.; Unequal sling lengths are needed because the CG is off-center.


Chain Hoist

Manual, electric, or pneumatic hoist that lifts via load chain. Rated by capacity and duty class; requires proper suspension, intact hook latch, and load path control.

Hang a 2-ton air chain hoist on the beam trolley.; This hoist is only rated for H3 duty—don’t use it for production cycling.; Inspect the load chain for twist and wear before use.


Choker Hitch

A sling configuration where the sling passes around the load and through a fitting or eye, tightening under load. Reduces capacity and may slip or crush certain shapes; use with caution and edge protection.

Use a double-wrap choker to reduce slippage on that pipe.; Apply choker reduction factors from the sling tag.; Avoid choking around sharp edges without padding.


Corner/Edge Protection

Protective pads, sleeves, or softeners placed between slings and load edges to prevent cutting and abrasion and to maintain sling capacity. Required whenever a sling contacts a sharp edge.

Add corner protectors where the roundsling crosses the beam flange.; That edge radius is too small—use a steel softener under the sling.; Web slings require edge protection on any sharp corner.


Crane Load Chart

Manufacturer tables and notes specifying allowable crane capacities by configuration, boom/jib length, radius, and setup. Includes critical notes, deductions, and limits that must be followed.

At 50 ft radius with main boom only, the chart shows 12,300 lb.; We’re on outriggers—use the ‘outriggers fully extended’ chart.; Account for the rigging and block as deductions per the load chart.


Critical Lift

A lift with elevated risk requiring enhanced planning, approvals, and controls. Criteria may include high capacity utilization, tandem picks, personnel exposure, unique rigging, or high consequence of failure.

Because it’s a tandem pick, classify it as a critical lift.; This lift exceeds 75% of chart—follow the critical lift checklist.; Engineering review is required per our critical lift policy.


D/d Ratio

The ratio of the contact diameter (D) to the sling or rope diameter (d). Smaller ratios increase bending stress and reduce efficiency; applies to wire rope, chain, and synthetic slings.

A D/d of 1.5 on that shackle pin will derate the wire rope sling.; Choose a larger sheave to improve the D/d for the fiber rope.; Use softeners to increase effective D at the beam edge.


Design Factor (Factor of Safety)

The ratio of minimum breaking strength to the rated working load. Set by standards and varies by product type; provides margin between WLL and ultimate failure.

Chain slings typically have a lower design factor than web slings.; Do not ‘add your own’ safety factor by overestimating WLL—use standards.; The engineer selected a 3:1 design factor for the custom BTH.


Dunnage

Material, often wood, used to protect, separate, and support loads during transport or staging. Prevents rolling, protects surfaces, and eases rigging removal.

Place dunnage under the transformer to allow sling removal.; Chock round stock with V-dunnage before tying down.; Use non-contaminating dunnage for painted components.


Exclusion Zone

A controlled area kept clear of personnel and nonessential equipment during lifts, jacking, or skidding to avoid exposure to the load path and swing radius.

Set cones to mark the exclusion zone under the load path.; Only the signal person enters the exclusion zone during the pick.; Pause the lift—someone just walked into the red zone.


Eye Bolt (Shoulder vs Plain)

Threaded lifting points. Shoulder eyebolts include a machined shoulder for properly seated angular loads; plain eyebolts are for straight vertical lifts only. Installation and orientation are critical.

Use shoulder eyebolts and orient the eyes in line with the load.; Derate for 45° on that shoulder eyebolt per the chart.; Replace that plain pattern eyebolt—this is not a vertical lift.


Fleet Angle

The horizontal angle at which rope approaches a sheave or drum. Excessive fleet angle causes rubbing, spooling damage, and reduced line life; keep within manufacturer limits.

Reposition the snatch block to reduce fleet angle to under 1.5°.; Poor fleet angle is crushing the first wrap on the winch drum.; Add a fairlead to control the fleet angle.


Ground Bearing Pressure (GBP)

Pressure imposed on the supporting surface by outriggers, jacks, or gantry legs. Must be calculated and reduced with pads/mats so it remains below soil or slab capacity.

Calculate GBP with pick load, rigging, and crane configuration.; Use 8x8 mats to lower GBP to under 3,000 psf on this asphalt.; Confirm the slab’s allowable bearing with structural engineering.


Hand Signals (Crane)

Standardized visual commands used by a qualified signal person to direct crane motion when radios are unavailable or as a backup. Defined by OSHA/ASME.

Use the ‘emergency stop’ hand signal if anything looks unsafe.; Agree on signals during the pre-lift meeting.; Spotter, give the ‘boom up’ signal clearly from the operator’s line of sight.


Identification Tag (Sling Tag)

Permanent tag on a sling showing manufacturer, material, capacity by hitch and angle, length, and unique ID. Required for use; slings without legible tags must be removed from service.

This roundsling is missing its tag—remove it from service.; Confirm the WLL for a 60° bridle on the tag.; Record the sling ID in the lift plan.


Inspection: Frequent vs Periodic

Frequent inspections are pre-use or daily checks by users; periodic inspections are documented, scheduled examinations by a designated person. Criteria and intervals follow standards and manufacturer instructions.

Log the quarterly periodic inspection for all shackles.; During frequent inspection, I found a cut in the web sling.; Tag out the hoist until it passes periodic inspection.


Jack-and-Slide (Skidding)

Moving heavy equipment by jacking to clear and sliding along low-friction tracks or skid beams using push-pull cylinders or winches. Controls include friction, alignment, and synchronized jacking.

We’ll jack-and-slide the press onto the foundation rails.; Use PTFE pads to lower friction on the slide beams.; Synchronize the jacks to keep the load level within 1/8 inch.


Job Hazard Analysis (JHA)

Structured review of a task to identify hazards and define controls before work begins. Documents steps, risks, mitigations, and responsible persons; updated when conditions change.

Include wind and pinch-point hazards in the JHA.; The JHA calls for tag lines and an exclusion zone.; Update the JHA when the lift radius changes.


Lift Director

The person responsible for execution, coordination, and safety of crane lifts per the plan. Ensures roles, communications, and site conditions are controlled.

The lift director will halt operations if wind exceeds limits.; Route all changes through the lift director.; The lift director confirmed ground conditions are verified.


Lift Plan

Document detailing load data, CG, rigging configuration, equipment capacities, path, ground conditions, personnel roles, communications, weather limits, and contingencies.

Attach sketches of pick points and sling angles to the lift plan.; The client requires a PE-stamped critical lift plan.; Revise the lift plan to reflect the new crane radius.


Load Securement (DOT/EN)

Regulatory-compliant methods to restrain loads in transport using chains, straps, binders, and blocking. Must meet working load limit requirements and use edge protection where needed.

Add two more tie-downs to meet FMCSA requirements.; Protect straps from cut edges with wear sleeves.; Check that aggregate WLL exceeds the cargo weight.


Minimum Breaking Load (MBL)

The minimum force at which a product is certified to fail under testing. WLL is derived by dividing MBL by the design factor; MBL itself is not a permissible working load.

The shackle’s MBL is 6 times its WLL per spec.; Engineering selected a roundsling with higher MBL for redundancy.; Never use MBL as the allowed working load.


Non-Destructive Testing (NDT)

Inspection methods (e.g., magnetic particle, dye penetrant, ultrasonic, radiography) that detect defects without damaging the part. Used for hooks, welded pad eyes, and BTH devices.

Perform MT on the lifting lug welds after fabrication.; UT the crane hook throat for internal flaws.; Schedule annual NDT for the spreader’s critical welds.


OSHA 1910/1926

U.S. regulations governing general industry (1910) and construction (1926) for cranes, rigging, qualifications, inspections, and safe work practices.

1926.1428 outlines signal person qualification.; 1910.184 applies to slings—follow its removal criteria.; Comply with 1926.1400 for crane operations on this site.


Outrigger Pads/Matting

Pads or engineered mats under outriggers to increase bearing area and lower ground pressure. Must be sized for load and site conditions to prevent settlement or failure.

Install 4-layer timber mats under the northeast outrigger.; Check mat capacity against the calculated outrigger load.; Use level, compacted ground before setting pads.


Pad Eye/Lifting Lug

A welded or bolted lifting point designed and rated for lifting. Requires proper orientation, weld sizing, and often proof testing and NDT; not intended for side loading unless designed for it.

The vessel has two pad eyes rated at 10 tons each.; Orient the shackle so the load line aligns with the pad eye.; Do not side-load the lifting lug; use a spreader if needed.


Professional Engineer (PE) Stamp

An engineer’s seal on drawings/calculations signifying professional responsibility and compliance with codes. Often required for critical lifts, custom BTH devices, and lift points.

We need a PE-stamped lift beam drawing before fabrication.; The client requires a PE stamp on the lift plan calculations.; Get the pad-eye design sealed for the 45° load case.


Proof Load Test

A controlled test applying a specified load above WLL to verify structural integrity and performance of lifting equipment (e.g., BTH devices, pad eyes, spreaders). Results are documented.

Proof test the new spreader to 125% with calibrated load cells.; Record deflection during the proof load and compare to limits.; Issue a proof-test certificate for the client’s QA file.


Qualified Rigger

An individual with recognized degree/certificate or extensive knowledge, training, and experience who can solve rigging problems. Defined by OSHA and company policies.

Only a qualified rigger may select and attach the rigging.; Show documentation of your rigger qualification.; A qualified rigger evaluated the sling angles for this pick.


Rated Capacity / Working Load Limit (WLL)

The maximum permitted load for equipment under specified conditions. Must not be exceeded; often marked on gear and defined per hitch type and angle.

The shackle’s WLL is 8.5 tons—our leg load is under that.; Always use hitch-angle WLL, not the vertical rating.; If the tag WLL is unreadable, remove the sling from service.


Reeving

The path of rope or chain through sheaves, blocks, and drums. Impacts mechanical advantage, line speed, and line pull; must follow manufacturer diagrams.

Reeve the snatch block for a 2-part line to double line pull.; Incorrect reeving is causing cross-overs on the drum.; Check fleet angle after changing the reeving pattern.


Rigging Triangle

The geometric relationship between pick points and the load that determines sling angles and leg tensions. Affects compression in spreaders and tension in sling legs.

The rigging triangle gives us a 45° leg angle—calculate leg loads.; Widen the pick points to reduce beam compression.; Use the triangle sketch in the lift plan to size hardware.


Round Sling

Endless synthetic sling of load-bearing yarns inside a protective sleeve. Very flexible but vulnerable to cuts, heat, and chemicals; requires edge protection and tag verification.

Use a polyester roundsling with wear pads on the sharp flange.; If the cover is torn exposing core yarns, remove it from service.; Check the tag for temperature limits before use near steam.


Side Loading

Applying load at an angle to components intended for inline loading. Often prohibited or requires derating for hooks, eyebolts, and some shackles.

Avoid side loading the hoist hook—use a swivel or spreader.; Eyebolts must not be side-loaded unless rated and oriented.; Switch to a hoist ring to accommodate the angular pull.


Signal Person

A qualified individual directing crane movement by standard hand or radio signals. Must understand crane operations, load dynamics, and site hazards.

Only the designated signal person talks to the operator.; Test radio communication before the pick.; If signals are unclear, the operator must stop and ask.


Sling Angle Factor (SAF)

A multiplier used to determine sling leg tension based on the angle between the sling and the horizontal (or vertical). Lower angles create higher tension; used to size slings and hardware.

At 30°, the SAF is high—upsize the sling.; Use the SAF chart to find per-leg load at 45°.; Raising the pick points improves the angle and reduces tension.


Snatch Block / Sheave

A pulley block, often with opening side plates, used to redirect line or gain mechanical advantage. Must match rope diameter and be rated for resulting line and anchor loads.

Rig a snatch block to turn the winch line 90 degrees.; The sheave groove must match the wire rope size.; Anchor loads double at the snatch block when doubling the line—verify rating.


Spreader Bar vs Lifting Beam

Spreader bars use top slings in tension and a compression strut; lifting beams carry load in bending between bottom slings. Selection depends on headroom, load geometry, and allowable compression.

Use a spreader to avoid compressing the vessel shell.; A lifting beam fits better under low headroom.; Check end fittings—compression for spreader, bending for beam.


Tag Line

A rope attached to a load to control swing and rotation. Handled at a safe distance; never wrapped around hands or tied off to fixed points during a lift.

Assign two spotters to manage tag lines on the long load.; Do not tie tag lines to fixed objects.; Add a second tag line to control tail swing in the wind.


Tension Multiplier (Sling Leg Tension)

The relationship showing how sling leg tension increases as the sling angle decreases. Used to convert load weight into per-leg tension for selecting slings and hardware.

With two legs at 45°, each leg sees about 0.707× the total load per leg—check sizing.; Compute the multiplier before choosing shackles.; The multiplier at 30° requires moving to a 3-leg bridle.


Vertical Hitch

A single-leg connection directly from the load to the hook. Stable only when the hook is above the CG; often requires tag lines to control rotation.

Use a vertical hitch on each end and a spreader to balance the beam.; A single vertical hitch will tip if the CG is off—add a second pick point.; Check headroom—vertical hitch gives maximum length.


Wind Limits

Maximum allowable wind speeds for crane operations and for loads/BTH devices, including gusts. Defined by manufacturers and site policy; high-sail-area loads require lower limits.

Suspend the lift—gusts are exceeding the 20 mph limit.; Large panels have high sail area—lower operational wind limits.; Secure the crane per the out-of-service wind chart.


Winch

A powered or manual drum device for pulling line used in lifting, pulling, or skidding. Rated by line pull on the first layer; capacity changes with drum layers and fleet angle.

This 10,000 lb winch has only 6,500 lb pull on the third layer.; Use a snatch block to double line pull and reduce drum load.; Keep the fleet angle small to prevent spooling damage.


Wire Rope

Multi-strand steel rope defined by construction (e.g., 6x36, IWRC), lay, and diameter. Inspection looks for broken wires, kinks, corrosion, and diameter loss; D/d ratio and sheave size are critical.

Select 6x36 IWRC wire rope for better flexibility.; Remove the sling—broken wire count exceeds discard criteria.; Mind the D/d ratio when rigging over small pins.


Was this page helpful? We'd love your feedback — please email us at feedback@dealstream.com.